Act as a senior structural engineer who reviews junior engineers' calculation packages before they go to the engineer of record. You check that loads, tributary widths and load combinations match the drawings and the project criteria, redo the arithmetic step by step, and list every discrepancy with the sheet or page it comes from. You do not size members, choose code values or approve anything: the engineer of record decides and seals.

Inputs:
- Project, structure type and governing criteria as given (code edition, design method, load values): [Project Criteria]
- What the drawings show (sheet numbers, spans, framing direction, supports): [Drawing Data]
- The calc package as written (assumptions, loads, results): [Calc Package]
- Serviceability limits stated in the criteria: [Deflection Limits]
- Open site conditions or unknowns: [Site Questions]
- Who receives the RFI and the response time: [RFI Recipient]

Generate:
1. Input match table: each assumption in [Calc Package] against [Drawing Data] and [Project Criteria], marked match or mismatch, with the source sheet.
2. Recalculation of the loads and demands step by step with the corrected inputs, units on every line.
3. Effect of each mismatch on the results, as a percent change.
4. Issues list for the junior engineer, ranked by effect.
5. Questions only the engineer of record can answer.
6. RFI draft for [Site Questions], addressed to [RFI Recipient].

Instructions

Paste the criteria, the sheet data and the calc exactly as written, including units. Use it in a tool your firm allows for project data. Recheck every line by hand or in your design software; the prompt checks consistency and arithmetic, it does not size members or choose code values. Variation: for a steel or concrete project, paste the same inputs for each member and ask for one match table per member. Tip: ask for units on every line; most errors show up as unit slips. Not engineering advice; a licensed professional engineer must verify every result, and this is never a substitute for stamped or sealed calculations. Local codes vary. Not affiliated with OpenAI.

Generated Output

This image was generated using the prompt above.

Structural Calc Check Prompt: Beam Loads, Math and RFI Draft - Result

Examples

Example Input

Project Criteria: two-story wood-frame house renovation, removing an interior bearing wall on the first floor; LRFD; the project criteria list dead load 15 psf and floor live load 40 psf; the calc uses the 1.2D + 1.6L combination.
Drawing Data: sheet S-101 shows new flush beam B-1 spanning 18 ft, simply supported on new posts P-1 and P-2. Floor joists frame into B-1 from both sides; joist span is 10 ft on each side. No wall or point load on B-1 from above.
Calc Package: B-1, span 18 ft, tributary width 8 ft. wD = 120 plf, wL = 320 plf, wu = 1.2(120) + 1.6(320) = 656 plf. Mu = 26.6 kip-ft. Vu = 5.9 kips. Live load deflection limit L/360 = 0.60 in.
Deflection Limits: L/360 for live load, L/240 for total load.
Site Questions: the existing footing under the location of P-2 is unknown; the contractor has not opened the floor yet.
RFI Recipient: the general contractor, response requested within 5 business days.

Example Output

1. INPUT MATCH TABLE
| Item | Calc | Drawings or criteria | Status | Source |
| Span | 18 ft | 18 ft | Match | S-101 |
| Tributary width | 8 ft | 10/2 + 10/2 = 10 ft | Mismatch | S-101 joist spans |
| Dead load | 15 psf | 15 psf | Match | Criteria |
| Live load | 40 psf | 40 psf | Match | Criteria |
| Combination | 1.2D + 1.6L | 1.2D + 1.6L | Match | Criteria |
| Point loads | none | none shown | Match | S-101 |
| Total load deflection | not checked | L/240 required | Missing | Criteria |

2. RECALCULATION (tributary width 10 ft)
wD = 15 psf x 10 ft = 150 plf
wL = 40 psf x 10 ft = 400 plf
wu = 1.2(150) + 1.6(400) = 180 + 640 = 820 plf
Mu = wu L^2 / 8 = 820 x 18^2 / 8 = 820 x 324 / 8 = 33,210 lb-ft = 33.2 kip-ft
Vu = wu L / 2 = 820 x 18 / 2 = 7,380 lb = 7.4 kips
Service reaction at each post = (150 + 400) x 18 / 2 = 4,950 lb
Deflection limits: L/360 = 216 in / 360 = 0.60 in (live); L/240 = 216 in / 240 = 0.90 in (total)

3. EFFECT OF THE MISMATCH
Tributary width 10 ft instead of 8 ft raises every line load by 10/8 = 1.25:
wu 656 to 820 plf (+25%), Mu 26.6 to 33.2 kip-ft (+25%), Vu 5.9 to 7.4 kips (+25%).
Deflection scales with load, so the live load deflection in the calc also rises by about 25%.

4. ISSUES FOR THE JUNIOR ENGINEER
1) Tributary width: use 10 ft per S-101 and rerun the B-1 member check for moment, shear and deflection.
2) Add the total load deflection check at L/240 = 0.90 in.
3) Post and footing design: carry the 4,950 lb service reaction (and the factored reaction, 7,380 lb) to P-1 and P-2.
4) Show the tributary width derivation in the calc so the reviewer can trace it to S-101.

5. QUESTIONS FOR THE ENGINEER OF RECORD
- Is any further load (partitions, finishes beyond 15 psf) intended on this floor?
- Should P-2 get a new footing regardless of what the RFI finds?

6. RFI DRAFT
To: General contractor
Subject: RFI, existing footing at new post P-2 (S-101)
Please open the floor at the location of P-2 shown on S-101 and report: footing size, depth, condition, and any signs of cracking or settlement, with photos and dimensions. The new post will carry a service load of about 4,950 lb. Please respond within 5 business days. Do not remove the existing bearing wall until the engineer of record confirms the footing.

Review aid only, not an engineering approval; the engineer of record checks and seals.